Cost overruns, new roof costs, plague Pottstown elementary projects

Cost overruns, new roof costs, plague Pottstown elementary projects

Posted: 03/21/14, 4:36 PM EDT | Updated: on 03/22/2014

Construction work at Rupert Elementary School is the most extensive of the four elementary school renovations, which is why staff and students were moved to the vacant Edgewood Elementary building for the year. (John Strickler/The Mercury)

POTTSTOWN — A $1.2 million price tag seems to be a little too high for school officials to bear, so the school board is being asked Monday to reject the bid to replace the roof at Rupert Elementary School along with some masonry work.

The concern about costs comes as the board is poised to approved more than $225,000 in unbudgeted expense for the construction work at Lincoln, Franklin and Rupert elementary schools.

Instead of accepting the $1.2 million roof bid, the administration is urging that other ways of getting the work done be pursued.


“It’s not that we’re not going to do it,” said Business Manager Linda Adams, “it’s just that we think that price is too high.”

The matter was brought first to the school board’s facilities committee at the March 13 meeting and the administration urged the committee to recommend a rejection of the bid to the full board.

Given that only two members of the board were not present at the committee meeting, and that no objections were raised at Thursday night’s work session meeting, the bid’s rejection seems all but assured.

Adams said there was only one bid submitted for the work and added that the administration hopes to find ways to get the work done by working through its energy consultant, Reynolds Energy.

Although the project will be undertaken during the same time as the renovation and expansion at the school, the district’s oldest, Rupert’s roof replacement was not part of the initial scope of the project.

“We had always intended to replace a portion of the roof, but not necessarily the entire roof,” Adams said of the original construction plans.

In fact, other than the portion of Rupert mentioned above, no roof replacements were anticipated in the $21 million plan to close Edgewood and renovate and expand Lincoln, Rupert and Franklin elementary schools.

Work at Barth Elementary School, which was renovated but not expanded as part of the project, was completed last summer and a new roof costing more than $660,000 was added on to that project after it was already underway.

Estimates for roof replacement and masonry work at Lincoln, Franklin and Rupert came to about $2.3 million in a consultant’s report which was not commissioned until construction on Barth was already underway and the design and bid work for the other three buildings complete or nearly so, an oversight school officials were at a loss to explain during an interview Wednesday.

According to estimates by the consultant, Wiss Janney, the cost for the work at Rupert should have come in closer to $855,500, which is why the administration is urging the rejection of the $1.2 million bid as being about $170,000 too high.

The estimated cost for roof and additional masonry work at Lincoln is $756,000 and is not expected to be undertaken for two years.

The estimate for roof and masonry work at Franklin is $679,000 and will wait until a year from now, except for a portion of the roof over the general purpose room, which was found to contain asbestos, Adams said. That work will be undertaken this summer.

A number of different roof types are being examined, and Adams pointed out that the Wiss Janney report also looked at the roofs and masonry at Pottstown Middle School and Pottstown High School, but not the administration building.

Adams said the district will not borrow additional money to pay for the roof and masonry work, but rather will fund the projects out of the operational budget.

She said the district has seen considerable savings from its self-health-insurance program with no rate hikes in two years and none anticipated for the coming year and that some of those savings may be tapped to pay for the roof work

As The Mercury has reported previously, the roof and masonry work is not being considered by the administration to be part of the elementary projects, which have themselves seen their own set of cost overruns.

In August, The Mercury reported that wiring for new computer and data systems were not included in the bid for the renovation of Franklin, Lincoln and Rupert elementary schools, an additional cost of an estimated $375,000.

In October, the full board was informed that the cost for additional electrical outlets, boxes, panel boards and the replacement of old wiring at the three schools has added another $388,601 to the price of the projects.

And on Monday, the board will likely vote to approve $225,780.36 in change orders for work at Lincoln, Rupert and Franklin, the largest portion of which is an addition of nearly $50,000 for “floor underlayment” at Rupert.

There was little discussion of these cost overruns at Thursday night’s board meeting.

However there was no absence of discussion, some of it a bit heated, the week before when the board’s facilities committee again discussed a $125,969 request to move some of the 12 new outlets in each of the new Barth classrooms because they were not placed where the teachers wanted them.

“When we did Barth, we missed the boat,” said school board member Ron Williams. “Sometimes, these things happen.”

Facilities Director Robert Kripplebauer said the fact that the district already has an electrical contractor on site presents “an opportunity to do it and do it right,” in terms of the outlets.

It was not a new discussion — the matter has been tabled three times — but it did come to a head when board member Thomas Hylton called the outlet complaints “trumped up” and Franklin Elementary School teacher Lindi Vollmuth, representing the teachers union, stormed out of the meeting saying she would not stay to hear the teachers “disparaged.”

“We’re so easy about spending other people’s money,” Hylton said prior to the unexpected conclusion of the discussion. “We have some parents in this town who pay full tuition to send their kids to schools with vastly fewer outlets than we have at these schools,” Hylton said.

“We’re defeating education if we don’t put these outlets where the teachers want them,” said board member Polly Weand, who insisted moving the outlets at Barth was about “equity” among all four of the elementary schools.

Vollmuth said that many Pottstown teachers “finance on their own” to bring materials to classrooms the district cannot afford and “it is not acceptable for us to be disparaged in public.”

Vollmuth said the request for the moved outlets was a result of technology requirements in the state-mandated curriculum.

In the end, no decision was made and Kripplebauer was asked to look at the matter again and see if a better, and less expensive solution could be found.

In the meantime, the board is expected to approve Monday the more than $225,000 in change orders at the three schools, a cost which does not, yet, include the $126,000 cost of moving the outlets at Barth

Leave a Reply